← Locate in the interconnected atlas

Europe / facility / reviewed 2026-09-28

FRA17 · Digital Park Fechenheim

Frankfurt facility handed over in 2023.

Mercury documented completion of the first colocation building on Digital Realty’s Fechenheim campus. The cited construction appointment began in October 2021.

Follow a relationship.

Direction records the stated relationship. A path through this web does not establish intent, causation or control beyond its individual records.

documented

Project client

Digital Realty → FRA17 · Digital Park Fechenheim

Digital Realty is the named client at the documented handover.

2023-06-23 · project client

documented

Prime contractor

Mercury → FRA17 · Digital Park Fechenheim

October 2021 appointment; civil, structural and architectural works completed by the 2023 announcement.

2023-06-23 · general contractor

documented

Electrical installation

Mercury → FRA17 · Digital Park Fechenheim

Construction scope included power distribution and generator installation.

2023-06-23 · electrical contractor

documented

Mechanical installation

Mercury → FRA17 · Digital Park Fechenheim

Construction scope included water-production, ventilation and fire-suppression systems.

2023-06-23 · mechanical contractor

documented

Located in

FRA17 · Digital Park Fechenheim → Germany

Geographic context; this edge does not imply government ownership or funding.

Date not isolated · location

proposal

Proposed data-center levy scope

FRA17 · Digital Park Fechenheim → AI companies & data-center operators

This named data-center facility falls within the sector addressed by the independent regeneration proposal. The liable legal entity, assessment basis and collection jurisdiction remain policy questions; this is not an enacted obligation or a payment.

Date not isolated · proposed levy coverage

What remains unresolved.

Facility links do not identify every workload

These project disclosures establish infrastructure relationships. They do not identify every tenant, AI workload, military customer, contract payment or measured environmental impact.

Next research step: Link any workload, funding or emissions claim to its own site-specific evidence.

Sources in this record.

  1. Mercury completes FRA17 on Digital Realty’s Frankfurt campusMercury · 2023-06-23 · source access 2026-09-28

    Contractor completion announcement; appointment was October 2021. General corporate maintenance capabilities do not establish a FRA17 maintenance contract.

  2. Paris Digital Park project case studyMercury · Publication date not isolated · source access 2026-09-28

    Undated portfolio page; identifies project period 2020–2025 and PAR8–PAR11 campus.

  3. Green Mountain delivers first data-center building to TikTokGreen Mountain · 2023-11-30 · source access 2026-09-28

    First-building handover precedes customer equipment installation. It is not a campus-wide operational commencement date.