← Locate in the interconnected atlas

Asia-Pacific / facility / reviewed 2026-09-28

Equinix SG5

Nine-storey Tanjong Kling data center, with a documented 2022 expansion and plumbing supplier.

Equinix’s April 2022 release describes added operating capacity. Master’s undated portfolio names specific building-services work; it does not identify an ongoing maintenance agreement.

Follow a relationship.

Direction records the stated relationship. A path through this web does not establish intent, causation or control beyond its individual records.

documented

Located in Singapore

Equinix SG5 → Singapore

A physical location relationship; it does not assign ownership or financing to the national government.

Date not isolated · located in

documented

Operates and expands SG5

Equinix → Equinix SG5

Equinix’s 2022 release describes the facility expansion.

2022-04-21 · facility operator

documented

Plumbing and cooling-water transfer

Master Construction Works → Equinix SG5

Supplier portfolio lists sanitary/plumbing work and AC make-up transfer for the cooling tower; appointment hierarchy undisclosed.

Date not isolated · building services

proposal

Proposed data-center levy scope

Equinix SG5 → AI companies & data-center operators

This named data-center facility falls within the sector addressed by the independent regeneration proposal. The liable legal entity, assessment basis and collection jurisdiction remain policy questions; this is not an enacted obligation or a payment.

Date not isolated · proposed levy coverage

Read the ledger.

announced investment

USD 86 million

Equinix SG5 announced expansion investment

Company-announced investment associated with expansion, not an audited payment total or the cost of every SG5 phase.

2022-04-21 · 2022 expansion announcement · documented

Inspect this record and its sources ↗

What remains unresolved.

Nine disclosed sites are a starting point

This layer covers selected buildings and campuses in seven jurisdictions. It is not a census of regional facilities or evidence that every site hosts AI or military workloads.

Next research step: Add facility-level permits, utility records, disclosed subcontractors and dated handovers. Keep operating sites, contracted phases and proposed expansions distinct.

Sources in this record.

  1. Multiplex completes Stage Two of NEXTDC S3 SydneyMultiplex · 2023-06-14 · source access 2026-09-28

    Contractor completion statement: Stage Two; Stage One was already occupied during these works.

  2. Gamuda secures contracts for Elmina Business Park hyperscale data centreGamuda Berhad · 2024-05-24 · source access 2026-09-28

    Separate construction and MEP awards. Original target dates are not evidence of actual completion or payments.

  3. Equinix expands its fifth Singapore data center, SG5Equinix · 2022-04-21 · source access 2026-09-28

    SG5 is a specific nine-storey facility in Tanjong Kling. Expansion announcement is not a disbursement account.

  4. Equinix Data Center SG5 — project portfolioMaster Construction Works · Publication date not isolated · source access 2026-09-28

    Lists plumbing/sanitary works and the cooling-tower AC make-up transfer system. Appointment chain and package dates are not given.

  5. Inside Yotta NM1Yotta · 2024-11-27 · source access 2026-09-28

    Operator account of the named Navi Mumbai building, on-site management and Shakti Cloud. Marketing performance/sustainability claims are not adopted as independent measurements.

  6. Khazna launches AUH6 in Masdar CityKhazna Data Centers · 2024-02-06 · source access 2026-09-28

    Operator launch identifies location, AI-related hosting and 31.8MW IT capacity; no individual hyperscaler tenant is named.

  7. GASTAT Data Center ProjectAlfanar Projects · Publication date not isolated · source access 2026-09-28

    Contractor labels the project completed and gives civil/electromechanical/cabling scope; completion date and current O&M provider are not disclosed.

  8. Data Center Rotem — Bank HapoalimElectra Group · Publication date not isolated · source access 2026-09-28

    Separately names construction, M&E, backup-generator and elevator roles. Current maintenance assignments are not given.