North America / facility / reviewed 2026-10-01
Colovore · Santa Clara engineering case
Santa Clara colocation facility with Therma engineering and design documented.
Legence describes Therma’s engineering and design for a 24,000-square-foot liquid-cooled facility. A 2014 report quotes its mechanical engineer on the cooling approach. Legence’s 2021 completion label conflicts with contemporary 2014 coverage, so this record does not assign a completion year or equate the case with a specific current Colovore site code.
Follow a relationship.
Direction records the stated relationship. A path through this web does not establish intent, causation or control beyond its individual records.
Named colocation customer
Colovore → Colovore · Santa Clara engineering case
Legence identifies Colovore as the Santa Clara data-center customer in the historical engineering case.
Date not isolated · facility client
Mechanical engineering and design
Therma → Colovore · Santa Clara engineering case
Legence attributes engineering and design to Therma; 2014 reporting quotes a Therma mechanical engineer on the cooling system. No current maintenance contract is inferred.
Date not isolated · mechanical engineering
Physical project location
Colovore · Santa Clara engineering case → United States
Santa Clara or San Jose, California; location alone does not establish a military use, tenant, or political affiliation.
Date not isolated · located in
Proposed data-center levy scope
Colovore · Santa Clara engineering case → AI companies & data-center operators
This named data-center facility falls within the sector addressed by the independent regeneration proposal. The liable legal entity, assessment basis and collection jurisdiction remain policy questions; this is not an enacted obligation or a payment.
Date not isolated · proposed levy coverage
What remains unresolved.
Resolve the Colovore case date and current site identity
Legence labels the case completed in 2021, while a 2014 report documents Therma’s participation. The selected sources do not reconcile those dates or identify which current Colovore site code covers the case.
Next research step: Obtain the original project record and facility address before assigning a completion year or current site code.
No named-site Therma maintenance contract verified
Therma markets maintenance, building automation and DCIM services, but the selected Santa Clara project records establish historical design or participation only. The general customer list does not give a facility, date or service term.
Next research step: Seek facility-specific current service contracts or operator statements with dates and exact scope before adding maintenance or DCIM edges.
Sources in this record.
- Therma data center servicesTherma · Publication date not isolated · source access 2026-10-01
Lists mechanical design/build, automation, DCIM, preventive maintenance and repairs as capabilities; does not identify a current contract at a particular facility.
- Colovore Data Center case studyLegence · Publication date not isolated · source access 2026-10-01
Attributes engineering and design of a Santa Clara Colovore facility to Therma. The page says completed 2021, while contemporary 2014 coverage already describes Therma project work; the date conflict is not resolved here. Performance and emissions figures are self-reported and excluded.
- Colovore Brings Liquid-Cooled Colo to Silicon ValleyData Center Knowledge · 2014-06-11 · source access 2026-10-01
Quotes a Therma mechanical engineer about the Santa Clara cooling system; corroborates a historical project role, not ongoing maintenance.
- Digital Realty 1100 Space Park Data Center, 3rd FloorDPR Construction · Publication date not isolated · source access 2026-10-01
Names Digital Realty as client, DPR as accountable design/build lead and Therma Corp. as a design-team partner. Does not state Therma was the general contractor or a current service provider.
- Fortune Data Centers Commences Operations of New Green Data CenterDPR Construction / Fortune Data Centers · 2009-04-28 · source access 2026-10-01
Identifies the Fortune San Jose first phase and names Therma among project partners. It does not allocate Therma a specific trade or an ongoing maintenance contract.