LD10 · London project

Historical London fit-out, 2017–2019.

Mercury’s project code is retained exactly. Its client is confidential, so this record makes no operator attribution from the code alone.

Follow a relationship.

Direction records the stated relationship. A path through this web does not establish intent, causation or control beyond its individual records.

documented

Fit-out and MEP

Mercury → LD10 · London project

May 2017–October 2019: mezzanine construction and data-hall fit-out with associated mechanical/electrical infrastructure.

Date not isolated · mep contractor

documented

Fire-protection installation

Mercury → LD10 · London project

Mercury’s Fire Protection Business Unit designed, supplied and installed the sprinkler system during the historical project.

Date not isolated · fire protection contractor

documented

Located in

LD10 · London project → United Kingdom

Geographic context; this edge does not imply government ownership or funding.

Date not isolated · location

proposal

Proposed data-center levy scope

LD10 · London project → AI companies & data-center operators

This named data-center facility falls within the sector addressed by the independent regeneration proposal. The liable legal entity, assessment basis and collection jurisdiction remain policy questions; this is not an enacted obligation or a payment.

Date not isolated · proposed levy coverage

What remains unresolved.

Facility identity needs careful matching

LD10’s client is confidential. The NorthC case does not identify its numbered Groningen building. Historical Colt names are not automatically mapped to a later operator.

Next research step: Use planning references or dated operator records to resolve identity without guessing from similar names.

Sources in this record.

  1. LD10 Data CentreMercury · Publication date not isolated · source access 2026-09-28

    Historical project period May 2017–October 2019. Client explicitly confidential; the facility code is not used to infer an operator.

  2. NorthC Datacenter, GroningenFireX · Publication date not isolated · source access 2026-09-28

    Explicit scope split: FireX designed, supplied and commissioned; Hamer installed. Generic maintenance offerings on the page are not a site maintenance appointment.

  3. Efficiënt onderhoud en beheer van datacenters bij Colt Technology ServicesSPIE Netherlands · Publication date not isolated · source access 2026-09-28

    Undated contractor-hosted case, credited to Datacenterworks. Names Amsterdam and Roosendaal, M&E maintenance and 24/7 hands-and-eyes services; current site ownership and contract continuity remain unverified.